PROJECTS

Industrial Projects
Various industrial projects completed

COMPLETED DESIGN PROJECTS

Process and Concept Design

  • 5000 t/a Liquid Fertilizing Plant
  • 28 t/a Modular Briquetting Plant
  • 13000l/h Flow Bin filling line
  • 120 000 ton Grain Storage Facility

Specialised Equipment

  • SAG and Ball mill
  • Conveyors (chain, bucket, belt etc)
  • Air Filters, Fans, Belt Feeders, Augers
  • Air Separators, Silos, Tanks, Compressors
  • Many more specialised equipment

COARSE PARTICLE SEPERATOR

Arcelor Mittal Saldanha

Scope of fabrication and delivery:

  • 4 x Coarse Particle Separator assemblies (scope of fabrication as per SANS. RC.361L13-M/FPA 601)
  • 4 x constant load spring hangers

Details:

Peak Manpower:

11

Location:

South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

February 2016 / 3 months

Description:

  • Final detail & workshop engineering
  • Manufacture / Fabrication
  • Inspection, supervision, quality assurance and testing prior to despatch
  • Procurement of standard parts
  • Transport and deliver to SITE

95MW ARC FURNACE FIRE DAMAGE REPAIR​

SCAW Metals – Germiston

Overview The Project Timeline:

  • Remove damaged equipment
  • Rig out damaged transformer
  • Rigging and installation of spare transformer
  • 33kV switchgear replacement
  • 400V MCC Replacement
  • MV Cable replacement & joints
  • Instrument replacement
  • 95MW Arc Furnace Transformer Replacement (125t with Oil)
  • Work complete in 3 weeks!

Details:

Peak Manpower:

50

Location:

Germiston, South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

3 weeks – April 2019

LBM MORGAN MILL

Scaw Metals – Germiston

Scope of Work:

  • Installation of Mechanical equipment
  • Oil Lubrication System
  • Hydraulic System
  • Cooling System
  • Electrical Systems
  • Alignment
  • Procurement of cables

Details:

Peak Manpower:

50

Location:

Germiston, South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

2 Months / Jul’ – Sep’ 2019

MECHANICAL EQUIPMENT INSTALLATION

Hosaf Fibres – Durban

Scope of Work:

  • Material Procurement & Certification
  • Detail fabrication drawings
  • Fabrication of 70 ton Structural steel components
  • Galvanizing of Steelwork
  • Installation of Steel structures
  • Installation of Mechanical equipment (Compressors, Blowers, Pelletizing Machines, Classifiers, Valves and Piping, Day Bin with Support Structure, Load Cells, Tube Bundles.

Details:

Peak Manpower:

22

Location:

Durban, South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

5 Months / May – Sep’ 2017

BEDFRAMES & PRESSURE VESSEL FABRICATION

Abeinsa Abengoa – !KaXu Solar One

Scope of Work:

  • Engineering & Fabrication Drawings
  • Design Verification according to ASME standards.
  • WPS & PQR Qualifications
  • Welder Qualifications
  • Material Procurement & Certification
  • Fabrication
  • NDT testing (X-rays & Die-pen testing)
  • AIA approval
  • Hydro testing
  • Sub-contractor Management (X-rays, AIA, Hydro testing)

Details:

Peak Manpower:

18

Location:

Germiston, South AfricaPofadder, Northern Cape, South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

2 Months / Jun’ – Jul’ 2014

TRUNK CABLING UNIT 2

Eskom – Kusile Power Station

Scope of Work:

  • Daily reporting and planning of cables to be installed
  • Cable Management System was implemented & reported on a daily basis
  • Total Cable Length: 306 977m
  • Number of Cables: 2240
  • Number of Terminations: 4480

Details:

Peak Manpower:

120

Location:

Emalahleni, South Africa

Contractor:

ABB/Lead Engineering and Projects

Duration / Finish:

11 Months Aug’ 2016 Jul’ 2017

MECHANICAL PIPEWORK REPAIR & PAINTING

Transnet Pipelines – Langlaagte Depot

Scope of Work:

  • Repair of main contractor’s punch items
  • Pre-fabricate and install manifold piping
  • Repair pipe supports and level out drain lines
  • Remove old paint and paint to specifications

Details:

Peak Manpower:

12

Location:

Langlaagte, South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

6 Weeks / Nov’ - Dec’ 2013

MANIFOLD MODIFICATION PROJECT

Transnet Pipelines – Tarlton Depot

Scope of Work:

  • WPS, PQR and Welder Qualifications to ASME standards
  • Material Procurement & Certification
  • Fabrication including NDT testing (X-rays)
  • Sandblast & painting
  • Installation on Site includes ½” to 10” piping, valves, safety valves, pipe supports, grouting.
  • Hydro testing on site
  • Sub-contractor Management (X-rays, AIA, Hydro testing)
  • Commissioning assistance

Details:

Peak Manpower:

45

Location:

Tarlton, Gauteng, South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

3 Months / Oct – Dec 2014

WET SCRUBBER PIPING

Group Five Civils – Ghana

Scope of Work:

  • WPS, PQR and Welder Qualifications to ASME standards
  • Material Procurement & Certification
  • Fabrication including NDT testing (Ultrasonic testing)
  • Sandblast & Galvanizing

Details:

Peak Manpower:

6

Location:

Ghana

Contractor:

Lead Engineering and Projects

Duration / Finish:

3 Weeks / Apr – May 2017

TG PRESSURE BALANCE COMPENSATOR

AMSA – Vanderbijlpark

Scope of Work:

• WPS, PQR and Welder Qualifications to ASME standards
• Material Procurement & Certification
• Fabrication including NDT testing (X-rays)
• Sandblast & painting
• Hydro testing at painters
• Sub-contractor Management (X-rays, AIA, Hydro testing)
• Delivery

Details:

Peak Manpower:

10

Location:

Vanderbijlpark, Gauteng, South Africa

Contractor:

Lead Engineering and Projects

FUEL OIL SOLIDS REDUCTION PIPING

NATREF – Sasolburg

Scope of Work:

  • Material Procurement & Certification
  • Fabrication of 1200 diameter inch piping
  • Removal and installation of Heat exchangers
  • Installation of piping
  • Insulation of piping
  • Supply, fabricate and install 20t structural steel
  • Electrical cable supply and termination
  • Supply and installation of Instrumentation
  • Pressure testing and painting of piping

Details:

Peak Manpower:

18

Location:

Sasolburg, South Africa

Contractor:

Lead Engineering and Projects

Mechanical Installation

HOSAF – Durban

Scope of Work:

  • Material Procurement & Certification
  • Detail fabrication drawings
  • Fabrication of 70 ton structural steel components
  • Galvanizing of steelwork
  • Installation of steel structures
  • Installation of mechanical equipment (Compressors, Blowers, Pelletizing machines, Classifiers, valves and piping, Day Bin with support structure, load cells, tube bundles

Details:

Peak Manpower:

80

Location:

Durban, South Africa

Contractor:

Lead Engineering and Projects

Duration / Finish:

5 Months / May - Sep 2017

NATURAL GAS BURNERS & PIPELINE INSTALLATION

AMSA – Vanderbijlpark

Scope of Work:

  • Material Procurement & Certification
  • Detail fabrication drawings
  • Fabrication of 40 ton structural steel components
  • Fabrication and installation of:
  • 150NB Sch 40 pipe 450 meter long
  • 4 X Burner hoods 4.5m diameter
  • Installation of steel structures
  • Installation of Mechanical equipment valves and piping

Details:

Peak Manpower:

15

Location:

Vanderbijlpark, Gauteng, South Africa

Contractor:

Lead Engineering and Projects